Workpackage 1: Project management

Deliverable numberDeliverable title Due date Status
D1.1 Project Plan (including an Evaluation Plan, QA Plan, Dissemination Plan, and Exit/Sustainability? Plan)August 2012Complete
D1.2 Project Web Page on JISC Web Site (including copy of accepted Project Plan) August 2012 Complete
D1.3 Project Web Site at Lead Institution August 2012 Complete  http://www.le.ac.uk/projects/preparde
D1.4 Consortium Agreement (for projects involving more than one institution)October 2012 Complete
D1.5 Mid-term report (including financial statement) January 2013merged with final report
D1.6 Final project report (including financial statement) May 2013 Project completed
D1.7 Completion Report (including financial statement) June2013 Project completed

Workpackage 2: Journal and data repository workflows

Deliverable numberDeliverable title Due date Status
D2.1 Journal workflows from author submission of datasets and papers, through review to publication. Feb 2013 complete
D2.2 Data repository workflows from ingestion of data, through data centre technical review, to DOI assignment to dataset Feb 2013 complete

WORKPACKAGE 3: Scientific review of datasets

Deliverable numberDeliverable title Due date Status
D3.1 GDJ-specific guidance for reviewers of data submitted to GDJ Mar 2013 complete
D3.2 Report and recommendations of suggested best practise for scientific reviewers of datasets Jun 2013 workshop delivered

WORKPACKAGE 4: Cross-linking between repositories and data publishers

Deliverable numberDeliverable title Due date Status
D4.1 Roadmap to tighter linking between journal publications and datasets, including data visualisation checks and interface improvements, for review processes and enhanced publications. Apr 2013 Merged with D4.2 - complete
D4.2 Worked and operational examples of cross-linking between publications and datasets. Jun 2013 Merged with D4.1 - complete
D4.3 Roadmap for implementation of data publication at California Digital Library. Jun 2013 Complete
D4.4 Business plan addressing sustainability of the partnerships and cross-linking between data journals and repositories.Jun 2013 complete

WORKPACKAGE 5: Data repository accreditation

Deliverable numberDeliverable title Due date Status
D5.1 Report on requirements for data centre accreditation. Jun 2013 Complete

WORKPACKAGE 6: Stakeholder Engagement and Dissemination

Deliverable numberDeliverable title Due date Status
D6.1 Workshop with funders, policy makers, researchers, data repositories and other interested parties, discussing the requirements and guidelines for scientific review of data. Dec 2012 complete - workshop held in Mar 2013. Follow on workshop held on the 24th June 2013, and the presentations from that workshop can be found at  http://www2.le.ac.uk/projects/preparde/events/what-does-peer-review-of-data-mean-part-2
D6.2 Workshop with funders, policy makers, researchers, data repositories and other interested parties, discussing the requirements and guidelines for cross-linking between journal publications and datasets.Mar 2013 complete - workshop held April 2013. Presentations can be found at CrosslinkingWorkshop
D6.3 Workshop with funders, policy makers, researchers, data repositories and other interested parties, discussing the requirements and guidelines for accreditation of data centres Feb2013 Complete. Presentations and more details at  http://www.dcc.ac.uk/events/idcc13/workshops - scroll down to Workshop 6: Data publishing, peer review and repository accreditation: everyone a winner? The workshop report can also be downloaded from IDCC Data Centre Accreditation workshop report